Wednesday 19 September 2012

Contract Law Case Summary 2012


PERSAND & PARTNERS CO LTD v CWA 2012 SCJ 61

With regard to the first point it relies on the case of Desbro Trading Ltd v Ragavoodoo Bros & Co, in the presence of the Central Water Authority [1997 SCJ 132]. That case also basically concerned the late execution of a contract for the timely supply of materials with a penalty clause in case of late delivery. It is distinguishable from the present one in that Ragavoodoo Bros & Co had not shown that the delay on the part of Desbro had resulted in Ragavoodoo being delayed in the discharge of its own contractual obligations to the CWA, whereas here it is the CWA itself, as a water supplying Authority for the whole island, be it for domestic or industrial use, which is the defendant. Therefore to that extent, whereas Ragavoodoo would have had to show that it had to pay penalty to the CWA for delay that cannot be the case for the CWA when the latter is itself the end user of the goods supplied, under the contract.

I therefore take the view that the terms of the contract which have undisputedly been accepted by the defendant should apply strictly and penalty is payable for delay as was the obvious express intention of the parties, subject to what the defendant acknowledged to be justified delay, because the plaintiff was not responsible for the same.

As regards the need to put the defendant “in mora” before entering the claim, counsel for the defendant has rightly referred to the relevant part of the case of Bourgault du Coudray v. Min Kan [1982 MR 33] on which the plaintiff seeks to rely in support of its contention. In that case the Court refers inter alia to Art 1139 of the French Civil Code then in force in Mauritius. Art 1139 of our Civil Code, enacted in 1983, is a textual replica of the same. It reads as follows:-

“1139. Le débiteur est constitué en demeure, soit par une sommation ou par autre acte équivalent, soit par l’effet de la convention, lorsqu’elle porte que, sans qu’il soit besoin d’acte et par la seule échéance du terme, le débiteur sera en demeure.” (Emphasis added).

And this is what the Court says at page 3 of its judgment in Bourgault du Coudray (supra):

That is why, when it is the intention of the parties that the “clause pénale” should become operative without a “mise en demeure” the practice is to add some such clause as “et ce, par la seule échéance du terme, et sans qu’il soit besoin de mise en demeure ou de toute autre formalité quelle qu’elle soit.(Emphasis added).

In the present case it is not disputed that the contract, admitted to be binding on the parties, to all the conditions of which the plaintiff stated it is agreeable in its letter of 8 May 1998, makes provision for penalty for late delivery to be payable to the defendant “without any notification of claim being sent to the plaintiff”. Therefore on the very authority relied upon by the plaintiff, the defendant had by the terms of the contract expressed the intention that there would be no need for any “mise en demeure”, and the plaintiff had agreed thereto. It cannot now be heard to turn round, and purport to go back on what was the common intention of the parties. (Emphasis added).

The evidence otherwise shows on a balance of probabilities that the plaintiff has been less than diligent in the execution of its part of the contract, not exclusively for reasons beyond its control, but also on account of delay on the plaintiff’s part to open the letter of credit which delay the plaintiff has remained eloquently silent about.

The plaintiff is therefore not entitled to its claim in toto, but only to part of it as will be seen below.

Counsel for the defendant has also aptly quoted from the judgment of the Supreme Court in the case of Sun Trust v. State of Mauritius [2004 SCJ 9] with regard to the legal basis for retaining an amount from the contract price as penalty for delay of delivery. It is apposite to quote the following therefrom with reference to note 61 of Encyclopedie Dalloz, Droit Civil Vol III Vo. Clause Penale:-
“61. ..................................................................... Comme l’exprime l’alinéa 1er de l’article 1152, conformément au principe posé par l’article 1134 du code civil: «lorsque la convention porte que celui qui manquera de l’exécuter payera une certaine somme à titre de dommages-intérêts, il ne peut être alloué à l’autre partie d’une somme plus forte ni moindre.» Forfaitaire, la peine doit s’exécuter telle qu’elle a été fixée par les parties. ”

The above must, however, be read subject to the provisions of Article 1147 of our Code Civil which reads:-
“Le débiteur est condamné s’il y a lieu, au paiement de dommages et intérêts, soit à raison de l’inexécution de l’obligation, soit à raison du retard dans l’exécution, toutes les fois qu’il ne justifie pas que l’inexécution provient d’une cause étrangère qui ne peut lui être imputée, encore qu’il n’y ait aucune mauvaise foi de sa part.(Emphasis added).

It is noteworthy that the defendant in the present case has, to its credit, decided to treat the plaintiff fairly and reasonably, by reducing the penalty proportionately for the part of the delay which the plaintiff had shown to the defendant was beyond the plaintiff’s control and for which it could not be blamed or held responsible.

MATIKOLA RAMKELAWON v ROSE BELLE S.E BOARD 2012 SCJ 62

This is a claim by way of plaint with summons for goods sold and delivered, as well as for damages for wrongful termination and/or breach of contract.

The first and principal matter in issue is whether the alleged defect in the products, supplied by the plaintiff, as invoked by the defendant in purported justification of its non payment for the same and its putting an end to the contract, was because the products did not contain active ingredients as per specification.

It would be apposite to consider the provisions of Article 1641 of the Civil Code, under the headings “De la garantie des défauts de la chose vendue”, which finds its application in the case in hand. Article 1641 provides:-
“1641. Le vendeur est tenu de la garantie à raison des defaults cachés de la chose vendue qui la rendent impropre à l’usage auquel on la destine, ou qui diminuent tellement cet usage, que l’acheteur ne l’aurait pas acquise, ou n’en aurait donné qu’un moindre prix, s’il les avait
connus.”

The vendor’s guarantee under Article 1641 concerns latent defects (“vices cachés”). One can read from Juris Classeur Vo. Vente: Garantie Légale Contre Les Vices Cachés. Art. 1641 a 1649: Fasc 30; Note 1:
“L’existence n’en est admise qu’au cas ou il présente une certaine gravité.”

It also appears from Note 6 that the defect aimed at must constitute:
“toute défectuosité qui empêche la chose de rendre, et de rendre pleinement, les services que l’on attend. Il résidera dans ………….. l’impossibilité de s’en servir dans les conditions satisfaisantes, les conséquences nuisibles produites à l’occasion d’une utilization normale.”

One also sees at Note 7, that it must be established that:
“La qualité faisant défaut soit une des principales que l’on reconnait à la chose”.

It cannot be disputed that in the case of herbicides, the proportion of active ingredients characterises the effectiveness or lack of it for the purpose for which it has been bought.
At Note 51 the relevant part reads:
“Il ne suffit pas que la chose soit atteinte dans une de ses qualities principales. Il faut encore, pour menacer le contrat passé, que le vice ainsi révélé présente une gravité suffisante …………….”

And the relevant part of Note 52 reads:-
“Les juges du fond semble disposer d’un pouvoir souverain pour apprécier la gravité de l’inexécution justifie la résolution ………………..”

The plaintiff’s case is aggravated by the fact that he purported to certify as to the analysis and quantity of the active ingredients himself, departing from the condition of the contract (condition 12 of the terms and conditions) that a certificate of analysis from an accredited laboratory had to be provided at the time of delivery. In spite of the defendant’s acceptance of delivery with such defective certificate of analysis, upon the problem arising, it has become clear that the plaintiff chose not to be strictly compliant with such condition at its own risks and perils.

Furthermore, the defendant has shown through witness Umrith’s evidence and report, which has remained unrebutted, that the plaintiff failed to comply with the requirements of the 6th schedule of the Dangerous Chemicals Control Act 2004 in that the labelling in respect of the Diuron containers supplied to the defendant by the plaintiff was incomplete inasmuch as it did not show the date of manufacture, the active ingredients and their concentration, the expiry date, and health hazards.

The matters highlighted above also show that the plaintiff had failed with regard to matters which struck at the root of the contract (“une atteinte dans une de ses qualités principales”) and constituted breaches which were so serious (“un vice présentant une gravite suffisante”) that the defendant was justified in treating the contract as at an end and to repudiate it on account of such fundamental breaches on the plaintiff’s part. The plaintiff has failed to perform its part of the contract in that what it in fact supplied to the defendant was fundamentally different from what it had contrasted to supply.

The plaintiff having acted in fundamental breach of contract, the defendant was entitled to repudiate the unperformed part thereof. I therefore hold that the plaintiff is not entitled to damages as claimed, or at all. He has only himself to blame for the fundamental breach of contract and cannot therefore pray in aid the fact that he had already ordered and stocked half of the contract order, and has only been able to sell for some Rs 200,000 elsewhere.

V5 CO. LTD. v KHODABAKUS  2012 SCJ 116

This is an appeal against a judgment of the learned Magistrate of the Intermediate Court dismissing a claim for damages by the appellant, then plaintiff, for the alleged breach of an option agreement for the purchase of the respondent’s property.

Three central issues namely, whether: (a) the learned Magistrate did not err in law in considering the nature and scope of the ‘levée de l’option’ by the appellant; (b) the respondent had furnished all the requested and requisite documents for the drawing up of the deed of sale and; (c) the entire burden to formalise the deed of sale rested on the appellant and that the respondent could simply adopt a passive role.

It was the clear intention of the parties in the agreement that the payment of damages under the ‘Clause Pénale’ would only arise ‘qu’au cas où je (respondent) ne me présente pas pour la signature du contrat.’ In that respect for all the given reasons, the learned Magistrate cannot be faulted when she reached the conclusion that the “triggering factor for the activation of clause 6 would be defendant’s failure to appear before a Notary Public to execute the deed of sale”. It is not in dispute that he was never summoned to appear before a Notary to execute the deed of sale.

But at no time did the appellant ever summon the respondent before a Notary as has rightly been pointed out by the learned Magistrate. It was clearly incumbent upon the appellant to summon the respondent before a Notary as per clause 6 of the ‘option’ agreement.

We therefore find no fault in the reasoning of the learned Magistrate in finding that the appellant cannot succeed in its claim inasmuch as it had failed to summon the respondent for the signing of the deed before the Notary.

On the issue of whether the whole burden rested on the appellant to formalise the deed of sale while the respondent could just adopt a passive attitude, we again agree with the reasoning of the learned Magistrate. The appellant did nothing for a relatively long span of time, following his ‘levée de l’option’ on 5 May 2007. It was only much later on 6 May 2008 that he initiated action for damages against the respondent and, this too, after learning that the respondent had sold the property to a third party. The learned Magistrate was right in finding, in view of the state of the evidence that, far from having adopted a passive role, the respondent has done his upmost to try and obtain a certified location plan. When he informed the appellant’s préposé at his office of his inability to obtain the said document, he was informed that he would be summoned before a Notary for the drawing up of the deed of sale. The learned Magistrate rightly considered that “it was for the Notary in charge of the sale to say that the SR & SP submitted was incorrect (if at all) and request a fresh one”. The appellant never in fact asked the respondent to attend the office of a Notary Public in accordance with clause 6 of the ‘option’ agreement after he had exercised his right to the ‘option’ on 5 May 2007.

For all the above reasons, we consider that the learned Magistrate cannot be faulted for concluding that, on a balance of probabilities, the appellant has failed to prove that the respondent has acted in breach of the ‘option’ agreement and is entitled to the payment of any damages.

NOVALIS INTERSERVICES LTD v THE ATTORNEY-GENERAL 2012 SCJ 194

This is an appeal from a judgment of the learned trial Judge dismissing a claim by the appellant, then plaintiff, against the defendant, now respondent, for damages for breach of contract or, in the alternative, for “rupture abusive des négociations avancées” after she had found, first, that there was no valid contract between the parties, let alone any breach thereof, and, secondly, that the withdrawal of the award of the tender was neither unreasonable nor of bad faith.

On that evidence the learned trial Judge found that the intention of the parties was that a valid contract would only come into existence once a written contract would have been duly signed by the parties. In the absence of any written contract, she concluded that the action for breach of contract must fail. The learned trial Judge also found that, in view of the series of negotiations following the letter of award of 16 October 1996, the several counter proposals of the appellant, the initial commencement date of the project, and the several disturbing matters relating to the internal affairs of the appellant company, the decision of the Registrar-General not to accede to yet a further postponement of the project and to withdraw the award could not be considered as having been unreasonable or in bad faith. She accordingly held that the alternative claim for damages for “rupture abusive des négociations avancées” must equally fail.

It is clear that the acceptance of the tender and the issue of the letter of award of 16 October 1996 could not constitute a contract between the parties, the more so as the letter of award itself required the appellant, in case it agreed with the terms and conditions laid down therein, to call upon the Registrar-General at a given date to sign the contract – which would start on a particular date and span over a period of two years – and provide the required performance bond and bank security for the advance payment. In the circumstances, we take the view that the learned trial Judge rightly concluded that the letter of awardclearly indicated that the intention of the parties was that there would be a written
contract duly signed by them after they would have agreed upon all the conditions.

The evidence on record shows that the parties were still negotiating even as late as August 1997, with the appellant always trying to steal a march over the client Department over the date of commencement of the contract – which we consider to be an essential term of the
contract. There was never any “accord de volontés”.

In the circumstances, the learned trial Judge was right in holding that there was no contract between the parties, and accordingly there was no breach of any contract and still less any requirement to have recourse to justice to terminate it. The first three grounds of appeal accordingly fail.

Now, the record shows that, as highlighted above, as from the issue of the letter of award, both parties entered into a series of negotiations, with the appellant always trying to secure more favourable terms for itself. The learned trial Judge was alive to that state of affairs and concluded that “the end result was that the parties were negotiating, in the words of French commentators, a ‘contrat par étapes’ ”.

She then referred to Précis Dalloz, Droit Civil, Les Obligations: François Terré, Philippe
Simler, Yves Lequette (5o Ed) at paragraph 177
En principe libre d’interrompre les pourparlers, chacun de ceux qui y
participent engage néanmoins sa responsabilité lorsque la rupture dont il
prend l’initiative présente un caractère abusif … …

En pratique, la mauvaise foi consistera à prendre l’initiative de la
négociation sans intention sérieuse de contracter, à seule fin de dissuader
le partenaire de négocier avec autrui ou pour obtenir la révélation de
certains secrets, à prolonger une négociation qu’on sait ne plus pouvoir
conclure ou encore à rompre ‘sans raison légitime, brutalement et
unilatéralement des pourparlers avancés’. Soucieux de ne pas
compromettre à l’excès la liberté contractuelle, les tribunaux exigent une
faute patente, indiscutable … …

before asking the question, rightly in our view, whether the Registrar-General acted unreasonably and in bad faith in withdrawing the award. In determining this question, she took into consideration -
 (a) the fact that after 03 April 1997, the appellant had been requested on no less than four occasions to come and sign the contract;
(b) the qualms of the Registrar-General in April 1997 which the learned trial Judge considered to be “understandable”;
(c) the refusal of the respondent to sign the contract as late as September 1997 and the time that had elapsed since the issue of the letter of award which itself indicated the initial date for the start of the data capture project as being 10 January 1997 before concluding that the stand of the Registrar-General on the appellant’s counter proposal made on 25 August 1997 could not be said to be so unreasonable as to amount to a “faute patente, indiscutable”.

In the light of the evidence placed before the learned trial Judge, we are unable to say that she was wrong.

No comments:

Post a Comment